What each gate of GDD checks, when it runs, who decides, its limits and what parks a change, by color. The values are those of the gdd/rules.toml that gdd init writes; see Configuration for every key.

Gates by color

A change's color comes from the paths it plans and touches (see zones.toml); its lane from its color, its scenarios and whether it is resumable (see Lanes). Read each column as one kind of change.

Green, fast Green, full Yellow, fast Yellow, full Red
G0 Setup Gate (once per project) before any change before any change before any change before any change before any change
Red zones approved before any change but a spike same same same same
G1 Scenario Gate never: no new scenarios when scenarios are new or changed never when scenarios are new or changed when scenarios are new or changed
Plan approved by the human no no no no always
Test mode before build mode no only with G1 yes yes yes
G2 Loop Gate every round every round every round every round every round
G3 Merge Gate yes yes yes yes yes
Mutation testing in G2 and G3 no no no (mutation = true turns it on) no (mutation = true turns it on) always
Reviewer no quick quick quick deep, security included
G4 Release Gate by the human no only with G1 no only with G1 always
Human stops 0 0 to 2 0 0 to 2 2: the sitting, then G4

Red is never in the fast lane. A spike follows a recipe of its own: see Spikes.

The core of GDD is always on for red: mutation testing, the Reviewer (deep) and the human G4. A rules file that switches any of them off for red is refused.

Lanes

Lane When What it changes
Fast Lane The color is not red, the change creates or changes no .feature that needs G1, and it was created with gdd new-change --resumable (another agent could pick it up from its ticket alone). Its rule is [color.<color>.fast]. With the tables of gdd init: no G1, no human G4, zero human stops; green also goes without test mode and without the Reviewer.
Full Lane Every other change. Its rule is [color.<color>.full].

Color beats work type and lane: a red change always takes the full lane and the core of GDD. The Orchestrator judges whether a change is resumable when it creates it; gdd classify prints the lane and why.

G0 Setup Gate

When: Once per project, at the end of Setup (phase 0), before any change can be prepared.

What runs: gdd selftest, the harness self-test, four checks:

  1. A failing test turns G2 red: with the file of [selftest] file set aside, every G2 command passes, or is held to its known debt in gdd/debt.toml as G2 holds it; with the failing test of [selftest] content planted there, one fails. A gdd/debt.toml gdd cannot read fails the check, with the reason.
  2. Editing a protected file is blocked: [protected] all covers gdd/rules.toml and .github/workflows/gdd.yml, and that workflow runs bin/gdd ci.
  3. Rollback works in pre: [release] rollback_pre passes, or the release is simulated.
  4. Zero scenarios counts as a failure: G3 counts none in an empty folder, and [acceptance] required is not false.

The result goes to .gdd/selftest.json and the log. gdd selftest exits with 1 unless all four pass (harness 4/4).

Who decides: The machines: gdd gate G0 ok --by machines. It opens only when docs/brief.md exists and the last self-test passed; a person cannot open it (--by human is refused).

Limits: None. Fix the harness and run gdd selftest again.

What it blocks: gdd prepare refuses every change while G0 is pending.

At G0 there is no zone map beyond what gdd init wrote: the harness and the supply chain are red, and unmapped code is yellow.

When it says no

Real messages, the most common first.

You run gdd prepare before G0 is open:

error: G0 pending: run the Setup (the gdd-setup command).

Main already fails a G2 command (here lint, on an unused import), so the self-test cannot see a failing test turn G2 red. Fix it, or record it as known debt with gdd adopt:

KO a failing test turns G2 red (G2 is red without it: lint)
OK editing a protected file is blocked (Path Guard and CI)
OK rollback works in pre
OK zero scenarios counts as a failure
harness 3/4

You try to open G0 while the last self-test is not 4/4:

error: G0 cannot open: the harness self-test is not 4/4 (bin/gdd selftest).

The Brief is missing:

error: G0 cannot open: docs/brief.md (Project Brief) is missing.

G1 Scenario Gate

When: At the sitting of a change, when the change creates or changes a .feature file inside [acceptance] dir and outside [acceptance] regression. Changing only regression scenarios needs no G1.

What runs: Nothing: the human reads the scenarios (gdd sitting <id> shows them) and approves or asks for changes. Approving G1 seals the scenario files of the change as its branch has them, with their SHA-256, in the record, hidden examples included.

Who decides: The human: gdd gate G1 ok <id> --note "...", or gdd gate G1 ko <id> to ask for changes.

Limits: G1 refuses hidden examples (<dir>/hidden/) whose step sentences no visible scenario has: test mode never sees them and could not write their steps. One sitting per change covers G1, the red zones and the plan.

What it blocks: gdd prepare refuses a change with new or changed scenarios without G1. After G1, any change to a sealed file fails Path Guard for every role (scenario approved in G1 and modified afterwards).

Red zones

The red zones of gdd/zones.toml need a human approval, once and again whenever any red zone changes: gdd gate zones ok --note "..." (only --by human). The approval keeps the red zones and their hash in .gdd/zones.json; approving them as they already are writes nothing. Until they are approved, only a spike can be prepared. gdd status says pending or changed.

The plan of a red change

A red change needs its plan approved by the human before it is prepared: the Orchestrator writes .gdd/changes/<id>/plan.md (what, how, risks, how to roll back), the human reads it at the same sitting, and gdd gate plan ok <id> records it.

When it says no

Real messages, the most common first.

The change has new scenarios that nobody approved yet, so gdd prepare refuses it:

error: New or changed scenarios without G1: a human must approve them (the gdd-change command).

You read the scenarios and ask for changes (gdd gate G1 ko cart-total):

G1 ko on cart-total (human).

The red zones of the project are not approved yet, usually on its first change:

error: Red zones not approved yet: the Orchestrator proposes them at the end of Discover. (bin/gdd gate zones ok --by human)

A hidden example uses a sentence that no visible scenario has:

error: G1 refused: hidden examples use step phrasings that no visible scenario has, so test mode can never write them. Reuse visible sentences with new data:
  - an empty cart

G2 Loop Gate

When: After every round of build mode; whenever a Builder runs bin/gdd g2 (test mode runs it to see its new tests fail for the right reason); and on a relaunch, before any Builder runs.

What runs, in order:

  1. Path Guard for the role, on what the change touched since its build started. When it fails, no command runs: a role that touched the gate configuration could make the commands its own.
  2. Each [g2] command of gdd/commands.toml, in the alphabetical order of their names, each within [limits] command_seconds. mutation* commands run only when the change needs mutation testing (red, or a rule with mutation = true).
  3. Path Guard again.
  4. In build mode, the scope check: a path outside the planned paths whose color is the change's or lower is accepted and listed in the Decision Inbox; a higher one fails.

The report goes to .gdd/changes/<id>/g2.json, and to the log (one line per command, one for Path Guard and one for the gate) unless an agent ran it.

Who decides: The machines. It passes when nothing failed. A command with known debt in gdd/debt.toml that fails only warns, unless it reports more than its count.

Limits: [limits] builder_retries rounds of build mode (3), at least one. Still red: [limits] replans replans (1), each an Orchestrator call that writes replan.md, a round of test mode when the replan ends with NEXT: test, one more round of build mode and G2. Only the Orchestrator widens the scope.

What parks: G2 still red after the rounds and the replans (G2 still red after 3 retries and 1 replan). Path Guard failing after a round of test mode (Path Guard failed after test mode: ...).

A relaunch whose code already passes G2 skips the Builder (resume_green in the decision).

When it says no

Real messages, the most common first.

A G2 command fails, here lint on an unused import. gdd g2 prints its report as JSON:

{"ok":false,"gate":"G2","color":"yellow","passed":["acceptance","architecture","types","unit","path-guard","scope"],"skipped":[],"failures":[{"name":"lint","ok":false,"code":1,"duration_s":0.0,"tail":"F401 [*] `os` imported but unused\n --> src/shop/cart.py:1:8\n ...\nFound 1 error.\n[*] 1 fixable with `--fix`.\n"}],"out_of_scope":[]}

The Builder used its rounds and the replan, and G2 is still red. The change parks; its Decision Inbox says:

## Parked
- G2 still red after 3 retries and 1 replan

The Builder in build mode edits a scenario approved at G1. Path Guard fails and no command runs:

{"ok":false,"gate":"G2","color":"yellow","passed":["scope"],"skipped":[],"failures":[{"name":"path-guard","tail":"features/cart_total.feature: protected path for builder-build\nfeatures/cart_total.feature: scenario approved in G1 and modified afterwards\nThe gate commands did not run: Path Guard must pass first."}],"out_of_scope":[]}

The Builder touches a red path the plan does not list:

{"ok":false,"gate":"G2","color":"red","passed":["acceptance","architecture","lint","types","unit","path-guard"],"skipped":[],"failures":[{"name":"scope","tail":"src/shop/payments/charge.py: outside the package and red (the change is yellow); remove it, or the Orchestrator widens the scope"}],"out_of_scope":[]}

G3 Merge Gate

When: Once G2 is green, and again on top of the latest main when main moved while the change was built.

What runs, in order:

  1. Path Guard, then each [g3] command (alphabetical, within command_seconds, mutation* only when needed), then Path Guard again, and the scope check in build mode, as in G2. The stack sheets put here the full scenario run (hidden examples included), the lock file, static security analysis, dependency licenses, secrets on the diff and mutation testing on the diff.
  2. The scenario count: zero scenarios in [acceptance] dir fail it when [acceptance] required is true or the change has scenario files of its own.
  3. The security exceptions ([[IgnoredVulns]] of osv-scanner.toml, [advisories] ignore of deny.toml): one without a reason fails it; the ones the change adds are listed in the Decision Inbox and at G4.
  4. When the change has a Reviewer: the review, at the depth of its rule. The Reviewer answers VERDICT: OK or VERDICT: KO as the last line of its review.

The report goes to .gdd/changes/<id>/g3.json and the log.

Who decides: The machines and the Reviewer. When both pass, gdd records G3 ok by machines, then merges.

Limits: Red G3: one fix by the Builder (fix=g3), G2, and G3 again, which decides. Reviewer KO: one fix (fix=review), G2, G3 and a second review that checks only the reasons of the first. Merges go one at a time; a change whose main moved takes the latest main and passes G3 again.

What parks: G3 still red after its fix (G3 still red after one fix). A KO, or a red G3, after the Reviewer's fix (Reviewer KO or G3 red after one fix). A conflict with the latest main (main moved under it and the merge has conflicts in ...). G3 red on top of the latest main.

After the merge, the merge commit carries the change's record (see Files), and the build and deploy_pre steps take it to pre.

When it says no

Real messages, the most common first.

A G3 command fails, here a dependency with known vulnerabilities (jinja2==2.10 in uv.lock):

{"ok":false,"gate":"G3","color":"red",...,"failures":[...,{"name":"security","ok":false,"code":1,"duration_s":1.0,"tail":"...Total 1 package affected by 6 known vulnerabilities (0 Critical, 2 High, 4 Medium, 0 Low, 0 Unknown) from 1 ecosystem.\n6 vulnerabilities can be fixed.\n...| https://osv.dev/PYSEC-2019-217      | 8.6  | PyPI      | jinja2  | 2.10    | 2.10.1        | uv.lock |\n..."}],"out_of_scope":[],...}

The Reviewer answered VERDICT: KO, the Builder fixed it once, and the second review still said KO. The change parks:

## Parked
- Reviewer KO or G3 red after one fix

G3 is still red after the Builder's one fix:

## Parked
- G3 still red after one fix

Main moved while the change was built, and the merge has conflicts:

## Parked
- main moved under it and the merge has conflicts in crates/gdd/src/lib.rs: merge main into change/gdd-upgrade in its worktree (/home/me/gdd/../gdd.worktrees/gdd-upgrade), settle the conflicts, commit, then gdd launch gdd-upgrade

G4 Release Gate

When: Once the change is merged and in pre.

What runs: tests_pre, then demo (gdd release pre); the change is in-pre whatever they say. The human G4 applies when the change is red, when it had G1 and its rule has g4_if_g1 = true, and always for a spike: the recipe pauses (.gdd/changes/<id>/run.json) with the Decision Inbox and the demo for the human. Otherwise the machines record G4 ok and promote the change at once.

Who decides: The human, with gdd resume <id> --g4 ok|ko|polish:

Answer What happens
ok promote (the same artifact, to production), then observe. The change is closed.
ko The change is rejected; production is untouched; its worktree goes.
polish --note "..." One more pass of the Builder with the human's notes (build mode, fix=polish, with its rounds and replan), then G3, the Reviewer, the merge when there is something new, pre, and G4 again. It replaces a KO; it is not an extra stop.

Limits: A promotion that fails leaves production untouched and the change waiting at G4: the same ok retries it. In [versions] mode = "auto", a promoted change with a changelog line gets its version once the promotion passed.

What parks: A change caught in the middle of a promotion (promoting) parks with a message to look at production first, so nothing is deployed twice. When observe fails, rollback runs and the change goes to rolled-back with a request for a hotfix.

When it says no

Real messages, the most common first.

You answer polish without saying what to polish:

error: polish needs your notes: gdd resume cart-total --g4 polish --note ...

You answer a change that is not waiting at G4:

error: Change cart-total is not paused at G4.

Someone tries to promote a change that needs a human G4 before the human answered:

error: This change needs a human G4 before promotion.

Production gets worse after the promotion: observe fails (here it prints error rate up), gdd rolls back and asks for a hotfix:

error: release.observe failed (exit code 1):
error rate up
--- end of output ---
error rate up
Rollback: ok
Production failed while observing: rolled back to the previous version. A hotfix is needed. Message in .gdd/changes/cart-discount/inbox.md

Learn

Learn (phase 5) has no gate: it only hardens.

  • gdd learn runs the [learn] tools of gdd/commands.toml once (duplication, unused code), keeps what each said in .gdd/learn/, lists the polish notes the human gave at G4 and the classes of finding that repeat in the Reviewer's KO reviews of two changes or more. It exits with 0 whatever the tools found.
  • The Orchestrator (gdd-learn command) turns each repeated error into one rule, lint, hook, test or line of docs/standards.md, and never loosens a gate. A proposal that changes gdd/ is red: the human decides.

Spikes

A change of type Spike answers one question and its code never reaches main.

Step What happens
Prepare Only G0 is needed; the red zones may still be pending. No G1, no plan, no test mode, no mutation testing, no Reviewer. Its color still picks its Builder.
Build Rounds of build mode (mode=spike) within builder_retries, then the replans, never test mode.
G2 Path Guard and an ADR: the branch adds or changes docs/adr/*.md with a ## Decision line. No command of gdd/commands.toml runs.
Budget After each agent call: the spike parks once its calls cost [spike] max_usd (5 USD).
G3, merge, pre None.
G4 Always the human. OK brings only the ADR to main; the spike's branch stays.

A spike with variants (--option once per option, or --variants <n>, 2 to 4) builds each variant on its own branch change/<id>-v<n>, one after another, each with the whole budget. It pauses at G4 when at least one variant passed its gate, and parks when none did (no variant passed its gate); gdd resume <id> --g4 ok --variant <n> brings that variant's ADR.

What parks a change

A parked change stops with a message in its Decision Inbox and keeps its worktree; relaunch it with gdd launch <id> once the cause is fixed.

Cause Where
G2 still red after the rounds and the replans G2
Path Guard failed after test mode G2
G3 still red after one fix; Reviewer KO or G3 red after one fix G3
Merge conflict with the latest main, or G3 red on top of it G3
The main checkout cannot take the merge: not on the main branch, or uncommitted changes in tracked files G3
An agent failed, or did not answer within [limits] agent_timeout_s any agent call
An agent changed GDD state, or the Reviewer changed a file any agent call
A spike reached its budget, or no variant passed its gate Spikes
Caught in the middle of a promotion G4
gdd park <id> <reason> by hand